7/24/2014 - Road Reconstruction Projects - Summer/ Fall 2014
Road Reconstruction Projects – Summer/Fall 2014
As part of the Town’s pavement management program, the following roads will be reconstructed through Summer and Fall: Barn Door Hill Road; Barry Place; Branch Road (western portion); Douglas Street; High Street; Somerwynd Lane and Thompsonville Road (from East Street North to Burbank Avenue).
Drainage work, to be done first, will involve replacement of deteriorated facilities, installation of structures, pipe and underdrains and replacing all existing catch basin tops. Road work will include recycling existing pavement and base material and installing 3” thick pavement with flat style curbing in areas of existing curbing or new areas for drainage purposes. The project, with duration of 4 months, is being coordinated through the Town Engineer’s office (860-668-3876).